Category:Roles: Difference between revisions

    From UNITApedia
    Line 21: Line 21:
    |-
    |-
    | I || Informed
    | I || Informed
    |}
    ==== Matrix of UNITA processes by responsibilities ====
    {| class="wikitable sortable"
    ! Process !! TTL !! WPL !! TT !! EC !! UO !! MC !! GB !! QEB + TT3.1 !! SA !! AP !! Other Projects
    |-
    | Internal Communication procedures
    | S || S || S || R || S || A || I || I || I || I || A
    |-
    | Task management
    | C/A || C/A || R || C/I || C/S* || A || I || I || C/I || S || A
    |-
    | Risk management
    | S || R || S || C/I || S || A || C/A || C || I || I || A
    |-
    | Issues and Decisions management
    | R || S || S || C/I || S || A || C/A || C || C/I || I || A
    |-
    | Project Changes
    | R || S || S || C/I || S || A || C/A || C || I || I || A
    |-
    | Document management
    | S || S || S || R || S || A || I || I || I || I || A
    |-
    | Quality management: Review and submission of deliverables
    | S || R || S || C/I || S || A || I || I || I || I || A
    |-
    | Payments management
    | R || S || A || C || I || I || A ||  ||  ||  ||
    |-
    | Project reports
    | S || S || S || R || S || A || I/A || I || I || I || A
    |-
    | colspan="12" | ''Note:'' “*” applies only to UNITA project’s Task management.
    |}
    |}

    Revision as of 13:32, 13 May 2025

    Roles and responsibilities

    Structure

    The UNITA governance and management structure is depicted in the following image:

    UNITA governance and management bodies.

    The following category present a description of each board, team, or individual role, outlining key aspects such as their composition, meeting frequency, tasks, and responsibilities.

    Consolidated Responsibilities

    Consolidated Responsibilities Assignment Matrix (RAM/RASCI)

    The Responsibility Assignment Matrix (RAM) is a way of representing and clarifying the roles and responsibilities involved in the project, as described in the previous section. The RAM is also known as a RASCI table, which stands for:

    RASCI Description
    R Responsible
    A Accountable
    S Supports
    C Consulted
    I Informed

    Matrix of UNITA processes by responsibilities

    Process TTL WPL TT EC UO MC GB QEB + TT3.1 SA AP Other Projects
    Internal Communication procedures S S S R S A I I I I A
    Task management C/A C/A R C/I C/S* A I I C/I S A
    Risk management S R S C/I S A C/A C I I A
    Issues and Decisions management R S S C/I S A C/A C C/I I A
    Project Changes R S S C/I S A C/A C I I A
    Document management S S S R S A I I I I A
    Quality management: Review and submission of deliverables S R S C/I S A I I I I A
    Payments management R S A C I I A
    Project reports S S S R S A I/A I I I A
    Note: “*” applies only to UNITA project’s Task management.